Quote:
Originally Posted by jazzrack
in all my years I have never edited a schedule, what do I need to do if all I want to do is remove most off days from generated schedule?
|
Lucky you
Well to remove off days you'd have to subtract 1 from all day= numbers starting with the first off day to the last day of schedule. Then find the second off day and repeat till done.
However, since most likely not all teams have the same off day, you have to be very careful you don't end up with 1 team playing 2 different teams on the same day.
Example: First off day is day 7. You'd have to subtract 1 from all days after that so that day 8 is day 7, day 9 is day 8, day 10 is day 9, and so on to the end of schedule.
Not an easy task and there are no shortcuts that I know of.